Construction Update

Construction on the pumpstation is nearly complete.

  • Final commissioning of the pump station is underway now.
  • Paving and site restoration are scheduled for the spring.
  • The beach access via the new stairway is expected to be available in mid-April 2024.

We appreciate your patience and understanding during this important upgrade.