September 23, 2022 Construction Update
Construction of the pump station upgrade portion of this project is substantially complete. All the process piping within the pump station has been replaced, a new motor and process control system has been installed, and the works are operational. This upgrade will significantly extend the operating life of this critical infrastructure.