Concept Design Report (Phase 1A) Complete

The final concept design report has been completed and was presented to the RDN Board on January 13, 2026. The work included a detailed evaluation of existing conditions and a comparative assessment of bridge type options for both the Nanaimo River and Thatcher Creek crossings. At the January 13 meeting, the Board approved the recommendation to proceed to detailed design for a 2.4‑metre‑wide stiffened suspension bridge at the Nanaimo River crossing and a 2.4‑metre‑wide truss bridge at the Thatcher Creek crossing.