Nanoose Bay Reservoir Improvement Project - Alternative Approval Process
The Regional District of Nanaimo (RDN) is proposing a project to accommodate planned growth and improve the long-term fire protection and drinking water infrastructure in the Nanoose Bay Peninsula Water Service Area (NBPWSA) in Electoral Area E of the RDN. The proposed project will include the renewal of the existing Arbutus Reservoir and construction of one additional reservoir on Notch Hill. These water service improvements are necessary to meet future water demand, security, and safety requirements and are not considered to be optional.
Reserve funds and Development Cost Charges (DCCs) will be used to fund approximately half of the proposed reservoir improvement costs. The remaining project costs could be borrowed from the Municipal Finance Authority on behalf of the property owners. An Alternative Approval Process (AAP) will be used to determine if the NBPWSA property owners support borrowing funds for this project, which will begin on August 14, 2024.
Due to numerous requests for the electoral response form ahead of the official start of the Alternative Approval Process on August 14, 2024, the form is now available at the following:
- Online on the Get Involved RDN Nanoose Bay Reservoir Improvement Project - Alternative Approval Process page here or on our RDN website here
- In person at the RDN Administration Office, 6300 Hammond Bay, Nanaimo
- By mail - call 250-390-4111 or 1-877-607-4111 to request a mailed copy
- By email vote@rdn.bc.ca
If less than ten per cent of electors within the NBPWSA submit Elector Response Forms through the AAP, this will be considered adequate support from the property owners involved and the borrowing proposal will go to the RDN Board for approval before the project moves forward as designed. More information about the AAP will be added to this webpage in August.
The Arbutus Reservoir, located on Link Place, has been in service since 1982 and requires renewal or replacement. Renewing the existing reservoir in-place has been determined to cost much less than any other alternatives and will allow the existing location to be re-used.
The need for an additional water storage reservoir on Notch Hill is identified in the Development Agreement with the Lakes District developer, as well as being part of the RDN’s capital improvement plan. As part of the development agreement, the RDN’s statutory right-of-way on Notch Hill will be expanded to accommodate another reservoir and no additional land will need to be purchased.
As outlined in the table below, the total reservoir improvement project budget is estimated to be $2.4M. The reserve funds and DCCs only cover about half of the total project costs. The remaining project costs could be borrowed from the Municipal Finance Authority and paid back by taxpayers over a 25-year period. If the project receives community support and proceeds to construction, property owners would pay a maximum of $465 each, or an additional $34/year for 25 years on their taxes. After construction is complete and all costs have been accounted for, property owners will be given the option to pay their share of the project costs as a lump sum (to save interest) or to amortize their share of the project costs (as debt) on their taxes. The final amount owing will depend on the lending rate in place at the time of borrowing.
Summary of Anticipated Project Funding:
Nanoose Bay Operating Budget | $24,772 |
Nanoose Bay Water Reserve Funds | $393,559 |
Development Cost Charge (DCC) Funds | $862,923 |
Long term borrowing by property owners | $1,197,795 |
Nanoose Reservoir Project Budget: | $2,479,049 |
For More Information and to Get Involved:
- Visit our What's New updates that will share information on this page as the project moves forward
- Explore this webpage to find out more about the proposed reservoir improvement project including staff reports and other documents in the document library
- Stay informed by clicking on subscribe, to leave your email address and receive email updates as the project moves forward
- Check out the FAQ's which provide answers to common questions on the Alternative Approval Process and the proposed project
- Attend a public information session in July or August
- Ask a question and we will do our best to answer it and share the information with all.