What's Happening on Site: Fall 2025

Exciting progress continues at the South Wellington site. Interior and exterior painting, window installation, signage and accessibility upgrades—including new stairs and a ramp—are all underway.
A major milestone was reached last week with the replacement of the fire suppression system holding tank. The new tank, weighing 15,960 lbs. and holding 2,716 liters, was carefully maneuvered into the basement with the help of a crane—an impressive feat for the project team.
Looking ahead, the electrical distribution panel is expected to arrive and be installed in November. Meanwhile, the RDN and the South Wellington and Area Community Association are working together on an operating agreement for the facility. An official opening date will be announced soon.
Stay tuned for more updates as we get closer to welcoming the community into this revitalized space!