Bowser Village Centre Wastewater Project
Consultation has concluded
In March 2017, the RDN was awarded a $7.6 million joint Federal and Provincial Clean Water & Wastewater Fund grant to provide the Bowser Village Centre with sanitary sewer servicing to support the community’s evolution into a “compact, complete community”. The proposed project includes construction of a sewer collection system, wastewater treatment plant and marine outfall for treated effluent.
If constructed, the treatment plant will collect wastewater produced by residents and businesses in the village centre and provide secondary treatment with additional UV disinfection which will meet or exceed Federal and Provincial treatment requirements. The treated effluent will then be discharged to the environment via a marine outfall approximately 2.3 km off shore at approximately 65 m of depth.
Want to learn more?
Please register (tab at the top right of this page) to receive notification of news and updates.
Visit the background documents for project history and technical information.
Contact the project team at bowserwastewater@rdn.bc.ca or 1-877-607-4111.
Looking ahead: Project updates will be posted on this page monthly and at milestones.
In March 2017, the RDN was awarded a $7.6 million joint Federal and Provincial Clean Water & Wastewater Fund grant to provide the Bowser Village Centre with sanitary sewer servicing to support the community’s evolution into a “compact, complete community”. The proposed project includes construction of a sewer collection system, wastewater treatment plant and marine outfall for treated effluent.
If constructed, the treatment plant will collect wastewater produced by residents and businesses in the village centre and provide secondary treatment with additional UV disinfection which will meet or exceed Federal and Provincial treatment requirements. The treated effluent will then be discharged to the environment via a marine outfall approximately 2.3 km off shore at approximately 65 m of depth.
Want to learn more?
Please register (tab at the top right of this page) to receive notification of news and updates.
Visit the background documents for project history and technical information.
Contact the project team at bowserwastewater@rdn.bc.ca or 1-877-607-4111.
Looking ahead: Project updates will be posted on this page monthly and at milestones.
-
July 6, 2018
Two items relating to the Bowser Village Wastewater Project will be brought before the Committee of the Whole on July 10, 2018. These items are:
1. Bowser Village Wastewater Project Update Report
- A project update will be provided for information. See the July 10 Meeting Agenda for details. (Agenda item 9.4 on page 3. Report and supporting documents, see pages 94 - 102.)
2. Bowser Village Sanitary Sewer Service Rates and Regulations Bylaw No. 1773
- The Rates and Regulations bylaw for the Bowser Sewer Service Area will be provided for consideration of three readings and adoption at the subsequent Regular Board Meeting, Tuesday July 24, 2018. See the July 10 Meeting Agenda for more information. (Agenda item 9.5 on page 3. Report and supporting documents, see pages 103 - 121.)
Consultation has concludedTwo items relating to the Bowser Village Wastewater Project will be brought before the Committee of the Whole on July 10, 2018. These items are:
1. Bowser Village Wastewater Project Update Report
- A project update will be provided for information. See the July 10 Meeting Agenda for details. (Agenda item 9.4 on page 3. Report and supporting documents, see pages 94 - 102.)
2. Bowser Village Sanitary Sewer Service Rates and Regulations Bylaw No. 1773
- The Rates and Regulations bylaw for the Bowser Sewer Service Area will be provided for consideration of three readings and adoption at the subsequent Regular Board Meeting, Tuesday July 24, 2018. See the July 10 Meeting Agenda for more information. (Agenda item 9.5 on page 3. Report and supporting documents, see pages 103 - 121.)
- A project update will be provided for information. See the July 10 Meeting Agenda for details. (Agenda item 9.4 on page 3. Report and supporting documents, see pages 94 - 102.)
-
June 28, 2018
The Regional Board completed first and second reading of the zoning amendment bylaw for the proposed Wastewater Treatment Plant site at the Regular Board meeting on Tuesday, June 26.
Please be advised that a Public Hearing regarding the rezoning of the proposed Bowser wastewater treatment plant site will be held on Monday, July 9, 2018 at 6:00 pm at Lighthouse Community Hall, 240 Lions Way, Qualicum Beach.
Click here for more information about the proposed zoning amendment and upcoming public hearing.
Consultation has concludedThe Regional Board completed first and second reading of the zoning amendment bylaw for the proposed Wastewater Treatment Plant site at the Regular Board meeting on Tuesday, June 26.
Please be advised that a Public Hearing regarding the rezoning of the proposed Bowser wastewater treatment plant site will be held on Monday, July 9, 2018 at 6:00 pm at Lighthouse Community Hall, 240 Lions Way, Qualicum Beach.
Click here for more information about the proposed zoning amendment and upcoming public hearing.
-
June 22, 2018
The zoning amendment application for the proposed Bowser wastewater treatment plant site will be brought before the Regional Board for first and second reading on Tuesday, June 26. For more information, click here to view the meeting agenda (see page 4, item 5.1.8).
Consultation has concludedThe zoning amendment application for the proposed Bowser wastewater treatment plant site will be brought before the Regional Board for first and second reading on Tuesday, June 26. For more information, click here to view the meeting agenda (see page 4, item 5.1.8).
-
June 8, 2018
The zoning amendment application for the proposed Bowser wastewater treatment plant site will be brought before the Electoral Area Services Committee for consideration of first and second reading on Tuesday, June 12. For more information, click here to view the meeting agenda (see page 3, item 7.3.2).
Consultation has concludedThe zoning amendment application for the proposed Bowser wastewater treatment plant site will be brought before the Electoral Area Services Committee for consideration of first and second reading on Tuesday, June 12. For more information, click here to view the meeting agenda (see page 3, item 7.3.2).
-
May 28, 2018
Thank you to everyone who attended the Public Information Meeting on Wednesday, May 16, 2018 about the rezoning of the proposed Bowser wastewater treatment plant site.
Missed the meeting? You'll find the posters and presentation in the documents library.
In the documents library you'll also find the May 2018 Project Update, providing the most up-to-date project information, and a letter from Island Health's Dr. Paul Hasselback discussing the recent discovery of Vibrio cholera and Norovirus in seafood products on the east coast of Vancouver Island.
Consultation has concludedThank you to everyone who attended the Public Information Meeting on Wednesday, May 16, 2018 about the rezoning of the proposed Bowser wastewater treatment plant site.
Missed the meeting? You'll find the posters and presentation in the documents library.
In the documents library you'll also find the May 2018 Project Update, providing the most up-to-date project information, and a letter from Island Health's Dr. Paul Hasselback discussing the recent discovery of Vibrio cholera and Norovirus in seafood products on the east coast of Vancouver Island.
-
May 14, 2018
Wondering what's new with the project? A project update newsletter is coming soon to residents' mailboxes in Electoral Area H. You can also find a digital copy of the May 2018 Project Update in the documents library.
Consultation has concludedWondering what's new with the project? A project update newsletter is coming soon to residents' mailboxes in Electoral Area H. You can also find a digital copy of the May 2018 Project Update in the documents library.
-
May 3, 2018
You’re invited to attend a Public Information Meeting about the rezoning of the proposed Bowser wastewater treatment plant site.
When: Wednesday, May 16, 2018. Doors open at 6:00 pm.
Where: Lighthouse Community Centre, 240 Lions Way, Qualicum Beach.
The meeting will provide information and seek input on the proposed rezoning of the site from Residential 2 (RS2) to Public 4 (PU4) to permit a wastewater treatment facility.
All are welcome to attend.
Click here for more information about the proposed zoning amendment.
Consultation has concludedYou’re invited to attend a Public Information Meeting about the rezoning of the proposed Bowser wastewater treatment plant site.
When: Wednesday, May 16, 2018. Doors open at 6:00 pm.
Where: Lighthouse Community Centre, 240 Lions Way, Qualicum Beach.
The meeting will provide information and seek input on the proposed rezoning of the site from Residential 2 (RS2) to Public 4 (PU4) to permit a wastewater treatment facility.
All are welcome to attend.
Click here for more information about the proposed zoning amendment.
-
May 2, 2018
In December 2017, the Regional Board adopted bylaws establishing the Bowser Village Sanitary Sewer Service and its funding mechanisms and directed staff to proceed with next steps on the project.
Since December, project staff and consultants have been hard at work on these next steps, including:
- Updating the collection system and treatment plant design
- Starting the permitting and approvals process by submitting the first several application packages to local, Provincial and Federal agencies.
- Communicating with First Nations
- Investigating outfall routing
- Initiating detailed design work on the marine outfall
Stay tuned to this section for What’s New on the project. To stay informed of project updates, please register by clicking the tab at the top right of the page.
Consultation has concludedIn December 2017, the Regional Board adopted bylaws establishing the Bowser Village Sanitary Sewer Service and its funding mechanisms and directed staff to proceed with next steps on the project.
Since December, project staff and consultants have been hard at work on these next steps, including:
- Updating the collection system and treatment plant design
- Starting the permitting and approvals process by submitting the first several application packages to local, Provincial and Federal agencies.
- Communicating with First Nations
- Investigating outfall routing
- Initiating detailed design work on the marine outfall
Stay tuned to this section for What’s New on the project. To stay informed of project updates, please register by clicking the tab at the top right of the page.
Timeline
-
Sewer Servicing Study
Bowser Village Centre Wastewater Project has finished this stage2015 - 2017
-
Clean Water & Wastewater Fund Grant Awarded
Bowser Village Centre Wastewater Project has finished this stageMarch 2017
-
Service Area Petition Process
Bowser Village Centre Wastewater Project has finished this stageJuly - August 2017
-
Public Open Houses
Bowser Village Centre Wastewater Project has finished this stageOctober 2017
-
Sewer Service Area Established and Project Funding Mechanisms Approved
Bowser Village Centre Wastewater Project has finished this stageDecember 2017
-
Detailed Design for the Collection System, Treatment Plant and Outfall Finalized
Bowser Village Centre Wastewater Project has finished this stageMay 2017 - January 2019
-
Submitted Permitting and Approval Packages
Bowser Village Centre Wastewater Project has finished this stageJanuary 2018 - February 2019 (waiting for authorizations)
-
Tenders for Construction of Collection System, Treatment Plant and Outfall
Bowser Village Centre Wastewater Project is currently at this stageFebruary 2019 - May 2019 (estimated)
-
Construction
this is an upcoming stage for Bowser Village Centre Wastewater Project2019 - 2020 (estimated)