Share Dam Decommissioning on Facebook
Share Dam Decommissioning on Linkedin
Email Dam Decommissioning link
The decommissioning of the existing weir is scheduled to begin on Friday, August 15, 2025, and will take approximately 2 months to complete. For public safety, the area around the weir, as well portions of Stump Farm Trail and Marsh Trail will be closed while the work is ongoing. Please be cautious and remain alert to construction activities while using the park and nearby trails.
The work will include:
- Demolition of the existing weir structure;
- Infill grading around the existing berm;
- Overflow channel excavation at the marsh outlet;
- New reinforced concrete grade control structure at the marsh outlet.
Share Final Dam Decommissioning Plan on Facebook
Share Final Dam Decommissioning Plan on Linkedin
Email Final Dam Decommissioning Plan link
The final Coats Marsh Dam Decommissioning Plan is complete and has been submitted and approved by Province. The final dam decommissioning design includes several key elements:
- Complete removal of the existing concrete weir structure;
- Placement of fill material to the west of the existing berm;
- Removal of accumulated sediment near the weir;
- Construction of a 1.2 m high concrete grade control structure at the marsh outlet. The structure does not enable storage or diversion of water within the marsh and is not considered a dam;
- Widening a portion of the outlet channel to mitigate beaver activity and improve flood conveyance capacity in the event of an upstream beaver dam failure.
Construction will occur in the late summer/early fall, with instream works being carried out during the least risk timing window of August 15 to September 15.
The final plan can be found in the Documents tab of this page.
Share Environmental Impacts and Mitigation Measures for Weir Pool Area on Facebook
Share Environmental Impacts and Mitigation Measures for Weir Pool Area on Linkedin
Email Environmental Impacts and Mitigation Measures for Weir Pool Area link
The consulting team has completed the Weir Pool Environmental Impacts and Mitigation Measures report for the Coats Marsh weir decommissioning project. The document includes detailed recommendations for the following:
- Replanting the weir pool area with native species following decommissioning.
- Removal and mitigation of invasive species, particularly reed canary grass.
- Minimizing the construction impacts on amphibians through an amphibian salvage program during construction and the potential creation of new amphibian habitats in the weir pool area.
These mitigation measures will be incorporated into the final decommissioning plan for the Coats Marsh weir.
The document is posted in the Documents tab of this page.
Share Beaver Dam Risk Assessment on Facebook
Share Beaver Dam Risk Assessment on Linkedin
Email Beaver Dam Risk Assessment link
The consulting team has completed the Beaver Dam Risk Assessment for the Coats Marsh weir decommissioning project. The document includes downstream flood mapping and commentary on the potential risks of various beaver dam breach and precipitation event scenarios. The document is posted in the Documents tab of this page.
Share Public Information Session on Facebook
Share Public Information Session on Linkedin
Email Public Information Session link
A public information session will be held from 11 a.m. - 3 p.m. on Saturday, January 20, 2024, at the Gabriola Art & Heritage Centre, located at 476 South Rd, Gabriola.
This is an opportunity to learn more about the project and discuss any questions you may have with RDN parks staff and the project consulting team.
The meeting will be drop-in style with no formal presentation.