Wellington Pump Station Upgrade Project
The Regional District of Nanaimo (RDN) is upgrading the Wellington Pump Station to:
- Increase capacity by approximately 40 per cent to meet future growth in the City of Nanaimo.
- Increase the reliability of the station by replacing aged infrastructure and adding stand-by power.
- Improve safety for RDN workers by eliminating confined spaces, and improving ventilation and lighting.
- Reduce nuisance odours.
- Improve beach access for City of Nanaimo residents.
- Respect archaeological values.
- Protect the environment.
The Wellington Pump Station, located at 5200 Fillinger Crescent in Nanaimo, was built in 1978. The pump station currently conveys approximately 25 per cent of the City of Nanaimo wastewater flows to the Greater Nanaimo Pollution Control Centre.
The viewing platform and beach access will not be available to the public during construction. Initial site works will begin in the summer of 2024 and are expected to be complete in the Summer of 2026.
How you can get involved:
- Subscribe to stay informed on this project. Subscribers will receive occasional emails with project updates.
- Explore this webpage to find out more.
The Regional District of Nanaimo (RDN) is upgrading the Wellington Pump Station to:
- Increase capacity by approximately 40 per cent to meet future growth in the City of Nanaimo.
- Increase the reliability of the station by replacing aged infrastructure and adding stand-by power.
- Improve safety for RDN workers by eliminating confined spaces, and improving ventilation and lighting.
- Reduce nuisance odours.
- Improve beach access for City of Nanaimo residents.
- Respect archaeological values.
- Protect the environment.
The Wellington Pump Station, located at 5200 Fillinger Crescent in Nanaimo, was built in 1978. The pump station currently conveys approximately 25 per cent of the City of Nanaimo wastewater flows to the Greater Nanaimo Pollution Control Centre.
The viewing platform and beach access will not be available to the public during construction. Initial site works will begin in the summer of 2024 and are expected to be complete in the Summer of 2026.
How you can get involved:
- Subscribe to stay informed on this project. Subscribers will receive occasional emails with project updates.
- Explore this webpage to find out more.
-
April 14, 2026 Update
The final phase of construction, Phase 3, has been awarded for construction. Below are some schedule and progress notes:
-
March to July, 2026: Exterior grading, construction of new control building and emergency generator pad
- Fun Facts:
- The new control building is required to safely accommodate the electrical equipment required to support population growth and the capacity upgrade of the pump station.
- The new control building will also house a new odour control unit, which will reduce the odour generated by the pump station.
- The emergency generator is required to ensure that sewage keeps moving in the system during extended power outages.
- What to expect: Construction noise, dust during dry weather excavation work, occasional traffic stops to allow equipment to move on/off site, and construction traffic.
- Fun Facts:
-
May 2026: Preparation of main pumpstation structure for internal refurbishment.
- What to expect: Noise from concrete cutting and modification work.
-
July 2026: Commissioning of new control building.
- What to expect: Noise during testing of new generator and control room equipment, possibility of localized odour during startup and testing of the new odour control system.
-
June to November, 2026: Operation of a new and temporary pumping system to have the sewer flow bypass the existing pump station structure, allowing it to be refurbished and upgraded on the inside.
- Fun Facts:
- Temporary bypass pumping is essential to be able to access the interior of the pump station and refurbish it.
- The temporary bypass pumping must be done during the summer while flows are lowest.
- The system has been designed to be powered from the new control building, avoiding the need for loud diesel generators to power the pumps.
- What to expect: Noise from the operation of pumps, which will start and stop as flows demand. Potential for localized odours as the temporary pumping system cannot provide a seal as effective as the pump station structure.
- Fun Facts:
-
June to November, 2026: Interior refurbishment and upgrade of the existing pump station structure.
- What to expect: Noise from construction works, construction traffic.
- December 2026: Construction complete, public access reinstated.
The final phase of construction, Phase 3, has been awarded for construction. Below are some schedule and progress notes:
-
March to July, 2026: Exterior grading, construction of new control building and emergency generator pad
- Fun Facts:
- The new control building is required to safely accommodate the electrical equipment required to support population growth and the capacity upgrade of the pump station.
- The new control building will also house a new odour control unit, which will reduce the odour generated by the pump station.
- The emergency generator is required to ensure that sewage keeps moving in the system during extended power outages.
- What to expect: Construction noise, dust during dry weather excavation work, occasional traffic stops to allow equipment to move on/off site, and construction traffic.
- Fun Facts:
-
May 2026: Preparation of main pumpstation structure for internal refurbishment.
- What to expect: Noise from concrete cutting and modification work.
-
July 2026: Commissioning of new control building.
- What to expect: Noise during testing of new generator and control room equipment, possibility of localized odour during startup and testing of the new odour control system.
-
June to November, 2026: Operation of a new and temporary pumping system to have the sewer flow bypass the existing pump station structure, allowing it to be refurbished and upgraded on the inside.
- Fun Facts:
- Temporary bypass pumping is essential to be able to access the interior of the pump station and refurbish it.
- The temporary bypass pumping must be done during the summer while flows are lowest.
- The system has been designed to be powered from the new control building, avoiding the need for loud diesel generators to power the pumps.
- What to expect: Noise from the operation of pumps, which will start and stop as flows demand. Potential for localized odours as the temporary pumping system cannot provide a seal as effective as the pump station structure.
- Fun Facts:
-
June to November, 2026: Interior refurbishment and upgrade of the existing pump station structure.
- What to expect: Noise from construction works, construction traffic.
- December 2026: Construction complete, public access reinstated.
-
March to July, 2026: Exterior grading, construction of new control building and emergency generator pad
-
October 24, 2025 Update
Phase 2 works are well underway and include sewer piping replacement on the pump station property, the addition of an electrical building and an emergency backup generator. Beach Access will continue to be restricted during this time due to construction hazards.
Phase 2 works will continue until the Spring of 2026.
Phase 2 works are well underway and include sewer piping replacement on the pump station property, the addition of an electrical building and an emergency backup generator. Beach Access will continue to be restricted during this time due to construction hazards.
Phase 2 works will continue until the Spring of 2026.
-
April 30, 2025 Update
Phase 1 of the upgrade project has been mostly completed. The first phase focused on foreshore works necessary to facilitate bypass pumping and improving wetwell access for RDN staff. The next phase of the project will begin early May 2025 and includes the addition of a new electrical building, emergency backup generator, odour control unit, and replacement of large diameter sewer piping from the station up to the intersection of Fillinger Crescent and Entwhistle Drive. Significant rock breaking (jack hammering) is not expected to occur during phase 2 and 3 of the project. Thank you for your patience while construction continues.
Phase 1 of the upgrade project has been mostly completed. The first phase focused on foreshore works necessary to facilitate bypass pumping and improving wetwell access for RDN staff. The next phase of the project will begin early May 2025 and includes the addition of a new electrical building, emergency backup generator, odour control unit, and replacement of large diameter sewer piping from the station up to the intersection of Fillinger Crescent and Entwhistle Drive. Significant rock breaking (jack hammering) is not expected to occur during phase 2 and 3 of the project. Thank you for your patience while construction continues.
Schedule
-
Phase 1 Construction - Foreshore
Wellington Pump Station Upgrade Project has finished this stageWork on foreshore and City of Nanaimo infrastructure
Summer 2024 to fall 2024
-
Phase 2 Construction - New Buildings & Sewer Tie in
Wellington Pump Station Upgrade Project has finished this stageUpdated: September 2025 to March 2026.
-
Phase 3 Construction - Bypass Pumping and Wetwell Upgrade
Wellington Pump Station Upgrade Project is currently at this stage- March to July, 2026: Exterior grading, construction of new control building and emergency generator pad
- May 2026: Preparation of main pumpstation structure for internal refurbishment.
- July 2026: Commissioning of new control building
- June to November, 2026: Operation of a new and temporary pumping system to have the sewer flow bypass the existing pump station structure, allowing it to be refurbished and upgraded on the inside.
- June to November, 2026: Interior refurbishment and upgrade of the existing pump station structure
- December 2026: Construction complete, public access reinstated.
Follow Project
Who's listening
-
Email jhaddou@rdn.bc.ca
