April 30, 2025 Update
Phase 1 of the upgrade project has been mostly completed. The first phase focused on foreshore works necessary to facilitate bypass pumping and improving wetwell access for RDN staff. The next phase of the project will begin early May 2025 and includes the addition of a new electrical building, emergency backup generator, odour control unit, and replacement of large diameter sewer piping from the station up to the intersection of Fillinger Crescent and Entwhistle Drive. Significant rock breaking (jack hammering) is not expected to occur during phase 2 and 3 of the project. Thank you for your patience while construction continues.