Potential Noise and Odour - Phase 3 Start

On October 29th, the Wellington Pump Station Upgrade Project completed Phase 2 and connected its new electrical building to the BC Hydro power grid. This milestone allows the project to move to the third and final phase of the project. For this phase, wastewater will be diverted around the pump station so the piping, electrical, and mechanical equipment inside the station can be replaced or refurbished.

Timing of the Work:

  • The work will begin on November 12th and be completed in the Spring of 2027.

What to Expect:

  • RDN’s contractor will be on site nearly 24/7.
  • Areas will be fenced off for public safety.
  • Construction noise will occur within regular work hours of 7 am – 6 pm on Monday to Friday, and 9 am – 5 pm on Saturday and Sunday.
  • The diversion pumps will be powered electrically, which eliminates the need for loud diesel generators that run constantly.
  • The backup generator will power the pumps only if a power outage occurs and will produce noise.
  • Temporary odours may be experienced. A new odour control unit is expected to reduce odours upon project completion.