The Bay Avenue Sewer Pump Station, located adjacent to 385 Bay Avenue in Parksville, BC, conveys about 85% of the City of Parksville's wastewater to the French Creek Pollution Control Centre.
The Bay Avenue Sewer Pump Station was originally constructed in 1978 and upgraded in 1997 and 2003. It must be upgraded again to increase pumping capacity and meet the current standards for Flood Construction Levels to protect critical electrical and control system components at the pump station and mitigate a potential environmental release.
The current approved budget is $6.4 million including engineering fees and construction.
How you can get involved!
To stay informed of project updates, please:
Sign-up to receive enewsletters by clicking the register or subscribe tab. By registering you will be kept up-to-date with progress on this project through our electronic communication.
Explore this page to find out more.
The Bay Avenue Sewer Pump Station, located adjacent to 385 Bay Avenue in Parksville, BC, conveys about 85% of the City of Parksville's wastewater to the French Creek Pollution Control Centre.
The Bay Avenue Sewer Pump Station was originally constructed in 1978 and upgraded in 1997 and 2003. It must be upgraded again to increase pumping capacity and meet the current standards for Flood Construction Levels to protect critical electrical and control system components at the pump station and mitigate a potential environmental release.
The current approved budget is $6.4 million including engineering fees and construction.
How you can get involved!
To stay informed of project updates, please:
Sign-up to receive enewsletters by clicking the register or subscribe tab. By registering you will be kept up-to-date with progress on this project through our electronic communication.
The RDN is happy to announce that the beach access is now open.
The contractor has installed a temporary wooden railing at the beach access. There will be a short-duration closure to the beach access in the next couple of months to replace the wooden railing with a permanent metal railing.
Thank you for you continued patience while we complete the upgrade to the Bay Avenue Pump Station.
Paving is now complete. Installation of the site gate and fencing is underway. Due to unforeseen challenges experienced during commissioning, beach access via the new stairway is delayed. Access is now expected to be available by the end of May 2024.
Additional challenges onsite have delayed construction. Completion of the project is now expected by the end of November 2023. The RDN appreciates the continued cooperation and understanding of area residents while the pump station is upgraded to improve capacity and safety.
Continued delays on delivery of electrical and controls components have further extended the project timeline. Commissioning of the new wet well is postponed until May 2023. Completion of the project expected in August 2023. New photos are added to the gallery.
The project will reach a milestone in March when wastewater flows will be redirected to the expansion wet well and we will start operating with the new control system. This will allow the renovation of the existing wet well to begin.
We recognize that the temporary loss of the beach access is inconvenient. The beach access is expected to be available to the public by the end of June 2023. The size and location of the construction site makes the work difficult to complete quickly. This, combined with labour shortages and supply chain issues, have lengthened the timeline. Our contractors and engineers are working hard and construction is progressing steadily.
The construction timeline for this project is extended. Beach access will continue to be unavailable until the end of construction. Please follow the signs posted on site.
Construction on this project begins July 19, 2021 and will continue for about one year. Please note that public beach access from Bay Avenue will not be available during the construction period.
At the RDN Regular Board Meeting on October 22, 2019, the RDN Board awarded the contract for detailed design for the Bay Avenue Sewer Pump Station Upgrade to Koers & Associates Engineering for $454,847 (Motion 19-413).
Page last updated: 10 Oct 2025, 12:36 PM
Signup Banner
Timeline
Preliminary Design
Bay Avenue Pump Station Upgrades has finished this stage
2017
Peer review of project components
Bay Avenue Pump Station Upgrades has finished this stage
2018
Detailed Design
Bay Avenue Pump Station Upgrades has finished this stage
2019 to 2020
Construction
Bay Avenue Pump Station Upgrades has finished this stage
July 2021 to April 2024
Paving and Site Restoration
Bay Avenue Pump Station Upgrades has finished this stage
Spring 2024
Beach Access Open
Bay Avenue Pump Station Upgrades has finished this stage
July 2024
Construction Completion
Bay Avenue Pump Station Upgrades is currently at this stage