Departure Bay Pump Station and Forcemain Expansion Project

Upgrading Key Sewer Infrastructure

The Regional District of Nanaimo (RDN), in partnership with the City of Nanaimo, is preparing to kick off construction on the Departure Bay Pump Station and Forcemain Expansion Project – a project that is necessary to upgrade wastewater services to meet current and future needs.

About the Project

This key project includes a renewal of the pump station at Departure Bay Beach, as well as the installation of four kilometres of new sewer forcemain along Hammond Bay Road, from the pump station to the wastewater treatment plant on McGuffie Road.

The current infrastructure is over 50 years old and at the end of its life. Upgrading this portion of the wastewater system is critically important – it currently moves 75 per cent of the City of Nanaimo’s wastewater to the treatment facility.

Latest News (Updated Nov. 2026)

  • November 2026: Intersection Changes - Departure Bay Road and Uplands Drive

    More intersection changes will take place this fall as part of the preparatory work happening in advance of next year’s active construction. This work is in addition to the work currently underway at Rutherford Road and Vanderneuk Road intersection.
    When: Late November – Late December (three-to-four weeks)
    Where: The intersection at Uplands Drive and Departure Bay Road
    Changes: Intersection will change from a one-way stop to an all-way stop
    These changes are being made to help facilitate traffic flow once one-way traffic is implemented in 2027.

    Read the full update here.

  • October 2026: Intersection Changes
    Intersection changes will take place this fall. This work is part of the preparatory work happening in advance of next year’s active construction.
    When: November 9 - Late Fall (six to eight weeks)
    Where: The intersection at Rutherford Road and Vanderneuk Road
    Changes: Intersection will change from a stop sign to a traffic signal
    For more information on these changes, read the news post here.

  • October 2026: The City of Nanaimo hosted two workshops in August and September to hear from community members about mobility upgrades along the Hammond Bay Road corridor. Click here to read the Engagement Summary Report.

  • October 2026 - Preliminary Ground Investigations Underway
    Preliminary ground investigations are underway to prepare for the upcoming Departure Bay Pump Station and Forcemain Expansion Project. This preliminary, preparatory work is expected to last until late fall. This is a required step before the start of larger construction expected in early 2027. Read the latest news post here.

    To facilitate this work, drivers and commuters can expect single lane alternating traffic in some areas. No changes to transit or pedestrian/cycling access are expected.

Keeping you Informed

We understand this project will be disruptive and of high interest to many in the corridor and throughout the area. This page will be the primary source for updates and information will be shared proactively as details are confirmed.

We invite you to:


Project Segment Map




Upgrading Key Sewer Infrastructure

The Regional District of Nanaimo (RDN), in partnership with the City of Nanaimo, is preparing to kick off construction on the Departure Bay Pump Station and Forcemain Expansion Project – a project that is necessary to upgrade wastewater services to meet current and future needs.

About the Project

This key project includes a renewal of the pump station at Departure Bay Beach, as well as the installation of four kilometres of new sewer forcemain along Hammond Bay Road, from the pump station to the wastewater treatment plant on McGuffie Road.

The current infrastructure is over 50 years old and at the end of its life. Upgrading this portion of the wastewater system is critically important – it currently moves 75 per cent of the City of Nanaimo’s wastewater to the treatment facility.

Latest News (Updated Nov. 2026)

  • November 2026: Intersection Changes - Departure Bay Road and Uplands Drive

    More intersection changes will take place this fall as part of the preparatory work happening in advance of next year’s active construction. This work is in addition to the work currently underway at Rutherford Road and Vanderneuk Road intersection.
    When: Late November – Late December (three-to-four weeks)
    Where: The intersection at Uplands Drive and Departure Bay Road
    Changes: Intersection will change from a one-way stop to an all-way stop
    These changes are being made to help facilitate traffic flow once one-way traffic is implemented in 2027.

    Read the full update here.

  • October 2026: Intersection Changes
    Intersection changes will take place this fall. This work is part of the preparatory work happening in advance of next year’s active construction.
    When: November 9 - Late Fall (six to eight weeks)
    Where: The intersection at Rutherford Road and Vanderneuk Road
    Changes: Intersection will change from a stop sign to a traffic signal
    For more information on these changes, read the news post here.

  • October 2026: The City of Nanaimo hosted two workshops in August and September to hear from community members about mobility upgrades along the Hammond Bay Road corridor. Click here to read the Engagement Summary Report.

  • October 2026 - Preliminary Ground Investigations Underway
    Preliminary ground investigations are underway to prepare for the upcoming Departure Bay Pump Station and Forcemain Expansion Project. This preliminary, preparatory work is expected to last until late fall. This is a required step before the start of larger construction expected in early 2027. Read the latest news post here.

    To facilitate this work, drivers and commuters can expect single lane alternating traffic in some areas. No changes to transit or pedestrian/cycling access are expected.

Keeping you Informed

We understand this project will be disruptive and of high interest to many in the corridor and throughout the area. This page will be the primary source for updates and information will be shared proactively as details are confirmed.

We invite you to:


Project Segment Map




Questions? Ask them here

Have any questions about the Departure Bay Pump Station and Forcemain Project? Share them here and the project team will get back to you!

Please Note:

  • We ask that only questions related to the project are asked here. Information provided here will not be shared with the RDN Board of Directors. 
  • To protect your privacy and the privacy of others, please do not include any information that could identify you or another person. Identifying information could include a person’s name, address, email or phone number. Questions that contain personal information will not be published.
Email
loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
  • Yes hi - will you be opening up the road between Sundown Dr & Gulfview Dr ? This currently is blocked off with barriers. This would help people get north without having to go south and then up north.

    Bryant Marshall asked 7 days ago

    Hi Bryant, using residential streets were considered, but it would bring commuter traffic onto roads that aren’t designed for it and raise safety concerns for people who live and walk there. Instead, there will be upgrades along the official detour route, including new traffic signals and other intersection changes. We recognize that this doesn’t remove the inconvenience, and we will continue to monitor this route and others and make adjustments where safety, time and costs allow.

  • Will there be bike lanes on both sides of the road. It has already too narrow for cars and trucks.

    JGL asked 11 days ago

    Hi JGL,
    The City of Nanaimo is preparing for the surface works that will take place during the later stages of the project. An FAQ document and accompanying drawings are now available to provide residents and community members with more information about the options being considered during this phase of construction.
    Click here to view the documents.

  • Given that the city has a sophisticated GIS system, could the city publish an online realtime map of the road areas affected and the detours, showing which sections at any given time have one-way traffic and in which direction, and which have two-way traffic, so that residents can plan their travel routes accordingly?

    valerior asked 13 days ago

    Hi Valerior, the City of Nanaimo utilizes Waze App and will input traffic impacts related to the project as they come. These changes will also show in Google Maps as well.

  • I am astounded to learn this and to think that from Stephenson Point Road to 7/11 and beach we will need to return home VIA Rutherford or Costco area. This is absurd and a huge waste of gas. There must be a cut through Linley Valley. An access through the park from Arrowsmith Road to Burma Road with a 15km/hour road including handicap parking lots along to said roadway to access the park would relieve much of this traffic and create the much-needed safety exits that the entire One way in/One way out Hammond Bay has created. Can you tell me how to push forward this initiate to create a cut through Linely Valley Park?

    wminbc asked 16 days ago

    Hi, thank you for taking the time to share your ideas about the detour routes. We understand the disruptive nature this project will have on the community as a whole. Many of the side roads were considered during the creation of the traffic management strategy, however, increased volume on residential side roads was not a viable option based on the predicted traffic volumes. Decisions around these topics are made by the project teams based on engineering requirements, safety standards, permits, budget and consideration of public input. We've passed your feedback and opinions to the project team. Thanks for reaching out.

  • Please advise what is happening at the southwest area of the intersection of Hammond Bay Road and Tiki Way, both now and through the course of construction. There is obviously a lot of heavy equipment currently working there. Thank you.

    Shamir asked 15 days ago

    Hello Shamir, the work you're seeing is related to the preliminary ground investigations currently happening to prepare for construction beginning in the new year. Read the news post here.

  • Is there anywhere I can find a work schedule? Dates, times and locations?

    Nolan asked about 1 month ago

    Hi Nolan,

    Thanks for your message. Timelines aren’t final yet, but construction on the Departure Bay Pump Station and Forcemain Expansion Project is expected to begin in early 2027.

    Preliminary ground investigations started in mid-October to prepare for the project. You can find more information here.

    If you have not yet already, be sure to subscribe to the project webpage as we'll share more details as they’re confirmed.

    Thank you

  • In the traffic management strategy there is text stating "The plan includes these key elements during active construction periods: ... Maintain existing pedestrian and cyclist access". Does this mean cyclists will be able to travel northbound on Hammond Bay road during construction?

    michael folkes asked about 1 month ago

    Hi Michael,
    Yes, cyclists and pedestrians will be able to move in both directions along Hammond Bay Road throughout the construction period.

  • Is there a way to receive daily or weekly updates on the affected work area? It seems as though Hammond Bay will be one way traffic some days, and other days might be alternating? Or certain sections will be? I have a child in before school care on Stephenson Point Road who attends Hammond Bay, so therefore need notice if routes are changing day to day.

    IslandLyss asked about 1 month ago

    Hello,

    Starting in early 2027, traffic will be one-way (southbound) only in segments with active construction. Two-way traffic will continue everywhere else. Northbound traffic will be directed to a bypass route via Departure Bay Road, Uplands Drive and Rutherford Road. Work may take place in more than one segment at a time, and we’ll share the timing for each segment in advance so you can plan your trips.

    To stay informed, subscribe to this page for project updates and expected traffic impacts to your email. The City of Nanaimo also shares citywide traffic impacts on Waze, which can help with planning your daily route.

     

  • Many are nervous at the overall timeline of the project and are expecting one (or more) years of delays based on past experience with roadworks. Has consideration been put towards construction operating hours, and either having long hours or extending into a night shift if it meant that the work could be completed sooner?

    Marie C asked about 1 month ago

    Hi Marie,

    Keeping to the schedule is important to the project team, and reasonable efforts will be made to complete the project within its four-year duration.

    The timeline reflects the complexity of the replacements and the limited capacity of the Hammond Bay Road corridor. The corridor must continue to support traffic, emergency services, transit, waste collection, water and sewer services throughout construction. Work hours are also shaped by the safety of workers and the public, and by traffic impacts. 

    The team has planned carefully to balance community needs with productivity and will keep looking for opportunities to finish sooner. However, this is a challenging construction zone, and the community should be prepared for a full four-year schedule.

  • Q's: 1. Do you have dates for each segment a-i? 2. Is Hammond Bay Rd. Going to be one way south bound for the whole time of 4 yrs?

    Mark Blaine asked about 1 month ago

    Hi Mark,

    Segment timing is still being confirmed and will be shared in advance of work starting in each segment. Work is expected to begin in Segments H and I and continue there for approximately the first two years of construction, then move southbound.

    One-way traffic will apply only while a segment is under active construction. Where no work is under way, traffic can flow in both directions. Work may also take place in more than one segment at a time.