Share on Facebook
Share on Linkedin
Email this link
16 Jul 2020
Please read the Notice to Residents for more information on new frontage trail on Hammond Bay Road between McGuffie Road and Shores Drive.
Share on Facebook
Share on Linkedin
Email this link
09 Jul 2020
Please read the Notice to Residents for a project update and information on the construction of a new frontage trail on Hammond Bay Road between McGuffie Road and Shores Drive.
Share on Facebook
Share on Linkedin
Email this link
19 Feb 2020
The Contractor has obtained a Noise Bylaw Exemption for February 11 and February 19, 2020. See the Notices for more information.
Share on Facebook
Share on Linkedin
Email this link
20 Dec 2019
The main construction works are expected to pause over the holidays from December 25, 2019 to January 1, 2020. During this time, construction support personnel will come and go to maintain systems. Construction will resume in the new year.
Share on Facebook
Share on Linkedin
Email this link
09 Dec 2019
The Contractor has obtained a Noise Bylaw Exemption for December 10 to December 12, 2019. See the Notice to Residents for more information.
Share on Facebook
Share on Linkedin
Email this link
02 Dec 2019
The project has achieved significant progress and is nearing completion. Construction and commissioning will continue into early 2020. Check out the Notice to Residents for a project update. Expectations for the coming months include:
- Noise - will remain similar as it has been through the fall. Intermittent noise will be generated to test new equipment, crush the last of the native rock, prepare the internal road, and backfill the secondary plant area.
- Truck traffic - will remain similar as it has been through the fall.
- Parking - construction crews will continue to park along McGuffie Road and Hammond Bay Road for the duration of the project.
- Odours - commissioning new systems may result in temporary strong odours.
- Late night or early morning work - the contractor will obtain City of Nanaimo Noise Bylaw Exemption Permits for any work required outside of noise bylaw hours.
Thank you for your continued patience as we complete this project. After the secondary treatment processes are successfully commissioned, GNPCC will produce substantially higher quality effluent and will reduce our impact on the environment.
Share on Facebook
Share on Linkedin
Email this link
26 Nov 2019
The Contractor will be crushing aggregate over the next month:
-
What to Expect - Activities will increase noise generated from the construction project, intermittently as required, for the duration of the time noted below. Noise associated with the aggregate crushing activities is expected to adhere to the City of Nanaimo Noise Bylaw
-
Dates - November 26 to December 21, 2019
-
Times - Monday through Saturday 7:30 a.m. to 6:00 p.m; Sunday 9:00 a.m. to 6:00 p.m.
Thank you for your continued patience as we complete this project.
Share on Facebook
Share on Linkedin
Email this link
26 Nov 2019
Older Public Notices can still be found in the Notices section on the right bar.
Share on Facebook
Share on Linkedin
Email this link
26 Nov 2019
The RDN has recently been approved for up to $6 Million
in funding from the Federal Gas Tax Fund to complete the GNPCC Secondary
Treatment Upgrade Project. Check out the News Release for more information.
Share on Facebook
Share on Linkedin
Email this link
26 Nov 2019
Construction will begin in May 2017 and will continue through to December 2019.
Typical construction activity will conform to the City of Nanaimo Noise Bylaw which states that noise due to construction shall not be caused before 7:00 a.m. and after 9:00 p.m. Monday to Saturday and before 9:00 a.m. and after 9:00 p.m. on Sundays and Statutory holidays.
Some work may continue outside of standard construction noise bylaw hours. For example, critical process modifications must be done at night when flows to the plant are lowest and plant flows can be shut down.